Pearl Harbor Memorial Bridge (Q Bridge)

Main features used in this application Construction stage analysis with creep and shrinkage Unknown load factor and lack of fit force for cable optimization Longitudinal & transverse post-tensioning Moving Load Analysis

Description on this project

The existing bridge was a plate steel girder, opened in January 1958. Its main span was 118m which was the longest plate girder in Western Hemisphere. For the replacement of the old bridge, several alternative studies were carried out and a concrete extradosed bridge was selected. Midas software was used for transverse review of the new bridge with the 3D model using solid elements.

 

  • Fig. midas Civil Analysis Model of Pearl Harbor Memorial Bridge (Q Bridge)

  • Fig. Stress Result of Pearl Harbor Memorial Bridge -1

  • Fig. Stress Result of Pearl Harbor Memorial Bridge -2

  • Fig. midas Civil Analysis Result Diagram of Pearl Harbor Memorial Bridge (Q Bridge)

  • Fig. Construction of Pearl Harbor Memorial Bridge -1

  • Fig. Construction of Pearl Harbor Memorial Bridge -2

Project Contact AECOM
  • Address

    7650 W Courtney Campbell Causeway, Tampa, FL 33607, USA

  • Introduction

    AECOM provides professional technical and management support services to both public and private sector clients. Services relate to Architecture & Design, Construction, Cost Management, Decommissioning & Closure, Economics, Engineering, Environmental Services, Planning & Consulting, Program, Technical Services, etc.

  • Website

    www.aecom.com

  • Email

Location

Connecticut, USA

Owner

Connecticut Department of Transportation (CTDOT)

General Contractor

O&G Industries / The Middlesex Companies

Engineering Consultant

AECOM

Construction Period

2014 - 2016

Type of Project

Extradosed Bridge

Size of Structure

157m Main Span, 308m Total Length